Wednesday, 23 September 2026

Rooppur Unit 1 Fuel Loading Delayed Over Licensing Hurdles

Staff Reporter, Pabna
Disclosure : 01 Apr 2026, 05:08 PM
Photo: Collected
Photo: Collected

The fuel loading for Unit 1 of the Rooppur Nuclear Power Plant (RNPP), originally scheduled for April 7, has been postponed due to a delay in obtaining the necessary commissioning license.

Science and Technology Secretary Md. Anwar Hossain confirmed the development, stating that while technical preparations were in place for the April 7 start, the mandatory clearance from the regulatory body is still pending.

"Fuel loading depends entirely on the regulatory agency’s clearance," the Secretary told the media. "The Bangladesh Atomic Energy Regulatory Authority (BAERA) is currently reviewing the documentation. We will fix a new schedule once the license is issued."

The Russian contractor had previously proposed the April 7 timeline. Under that plan, the plant was expected to begin trial generation by July, initially supplying 300 megawatts (MW) to the national grid before reaching its full 1,200 MW capacity by December.

Project officials noted that this delay will naturally push back the power generation timeline. The fuel loading process typically takes one month, followed by approximately two months to reach the "criticality" or chain reaction stage. Generally, it takes 10 to 11 months from the start of fuel loading to achieve full-scale commercial production.

Despite the setback, officials from the Bangladesh Atomic Energy Commission (BAEC) remain optimistic, hoping to secure the license and begin fuel loading by the end of this month. They emphasized that all physical construction and technical inspections for Unit 1 are complete.

"The regulatory body is independent; they will only approve the license once they are 100% satisfied with the safety protocols," a senior BAEC official stated on condition of anonymity.

Dr. Mahbubur Rahman, Project Director of Nuclear Regulatory Infrastructure at BAERA, declined to comment, noting he is currently occupied with the final review at the Rooppur site.

The $12.65 billion project, which began in 2017, has seen 81% of its budget utilized. While Unit 1 is in the final commissioning stage, Unit 2 is over 70% complete. Although the project deadline was recently extended to 2027, this latest delay adds fresh uncertainty to the completion of the country’s first nuclear power plant.

  • Latest

  • Popular

International Media Summit - 2026 Held in Jamalpur, Bihar

1

Does a Vegetarian Diet Prevent Cancer?

2

Missing Child Found Dead in Sack in Bhola's Borhanuddin Upazila

3

DeepSeek and OpenAI to Brief UN Security Council on AI Risks

4

Saudi Arabia Restarts Oil Pipeline, Global Oil Prices Drops

5

China Opposes US Threat to Ground Iranian Airlines Globally

6

DSE Targets 10 Blue-Chip Listings by 2027

7

Taylor Swift to Break MTV Video Music Awards Record as Madonna Leads Nominations

8

Zidane Begins New Era as France National Team Coach

9

Bus Fares Rise by 17 Paisa Per Kilometre After Fuel Price Hike

10

Motorcyclist Killed in Pabna-Ishwardi Highway Bus Accident

11

Mbappe Denies Rumors of a Feud with Dembele Over Ballon d'Or Comments

12

Six Foreigners Remanded in Cox's Bazar Cyber Fraud Case

13

Witness Describes What Happened Inside Gazi Nazrul’s NAM Bhaban Flat

14

Typhoon Dujuan Hits Japan: 4 Dead, Thousands Without Power

15

Is Trump-Tarique Meeting Possible During UNGA visit?

16

US-China Summit / Xi Jinping to Press Trump on Taiwan Weapons Sales at Washington Summit: REUTERS

17

United States to Reopen Cold War Military Bases in Greenland

18

Prime Minister Arrives in New York for 81st UN General Assembly

19

Youth Urge Rapid Formulation of FOPL Regulations

20