Sunday, 08 November 2026

Rooppur Unit 1 Fuel Loading Delayed Over Licensing Hurdles

Staff Reporter, Pabna
Disclosure : 01 Apr 2026, 05:08 PM
Photo: Collected
Photo: Collected

The fuel loading for Unit 1 of the Rooppur Nuclear Power Plant (RNPP), originally scheduled for April 7, has been postponed due to a delay in obtaining the necessary commissioning license.

Science and Technology Secretary Md. Anwar Hossain confirmed the development, stating that while technical preparations were in place for the April 7 start, the mandatory clearance from the regulatory body is still pending.

"Fuel loading depends entirely on the regulatory agency’s clearance," the Secretary told the media. "The Bangladesh Atomic Energy Regulatory Authority (BAERA) is currently reviewing the documentation. We will fix a new schedule once the license is issued."

The Russian contractor had previously proposed the April 7 timeline. Under that plan, the plant was expected to begin trial generation by July, initially supplying 300 megawatts (MW) to the national grid before reaching its full 1,200 MW capacity by December.

Project officials noted that this delay will naturally push back the power generation timeline. The fuel loading process typically takes one month, followed by approximately two months to reach the "criticality" or chain reaction stage. Generally, it takes 10 to 11 months from the start of fuel loading to achieve full-scale commercial production.

Despite the setback, officials from the Bangladesh Atomic Energy Commission (BAEC) remain optimistic, hoping to secure the license and begin fuel loading by the end of this month. They emphasized that all physical construction and technical inspections for Unit 1 are complete.

"The regulatory body is independent; they will only approve the license once they are 100% satisfied with the safety protocols," a senior BAEC official stated on condition of anonymity.

Dr. Mahbubur Rahman, Project Director of Nuclear Regulatory Infrastructure at BAERA, declined to comment, noting he is currently occupied with the final review at the Rooppur site.

The $12.65 billion project, which began in 2017, has seen 81% of its budget utilized. While Unit 1 is in the final commissioning stage, Unit 2 is over 70% complete. Although the project deadline was recently extended to 2027, this latest delay adds fresh uncertainty to the completion of the country’s first nuclear power plant.

  • Latest

  • Popular

Bangladesh Bank Eases Import Rules for 11 Essential Commodities Ahead of Ramadan

1

Two-Year-Old Girl Drowns in Pond in Bhola

2

National Revolution and Solidarity Day Observed in Dimla

3

Student Injured in Gas Leak Fire at Nazrul University Hall

4

Samira Khan Mahi Crowned Miss Universe Bangladesh 2026

5

Legal Notice Served on Actress Pori Moni over Alleged Journalist Harassment and 'insulting'National Anthem

6

Gadi Eisenkot on the Brink of History: How Different Is He from Netanyahu?

7

4,500 Litres of Condensate Stolen by Tapping Pipeline in Habiganj

8

Corruption Has Weakened Many Cooperatives: President

9

King’s 61 Gives West Indies Solid Start on Fourth Morning

10

Bangladesh Dollar Rate Tops Tk124 as Foreign Reserves Decline

11

Syria Denies Reports of Troop Deployment to Yemen for Saudi War

12

Fish Prices Put Popular Varieties Beyond Reach of Lower-Middle-Income Families

13

Intellectual Corruption Has Hurt Judiciary More, Says Law Minister

14

Tahshif Murder Case: Dip Sent to Jail After Remand

15

PM Warns of Tough Response to Conspiracies, Invokes Spirit of November 7

16

Who Is Behind the Looting of Stones from the Teesta River?

17

PM Tarique Rahman Leads Massive Rally on National Revolution and Solidarity Day

18

Songwriters Hall of Fame 2027 Nominees / Lady Gaga, Shakira, Pink, Jack White, Boy George and will.i.am

19

Bangladesh vs West Indies 2nd Test / Hridoy's Record 242 Rescues Bangladesh Against West Indies

20