The Rooppur Nuclear Power Plant has successfully connected to Bangladesh's national grid for the first time also supplying 350 megawatts (MW) of electricity on a trial basis on Tuesday afternoon.
Power transmission from the plant's first unit began at 3:13 pm in the presence of Science and Technology Minister Fakir Mahbub Anam, according to a press release from the Bangladesh Atomic Energy Commission. Earlier, the Science and Technology Minister, the Energy Minister and senior ministry officials arrived at the site by helicopter to witness the milestone.
Under the initial test phase, the plant will supply electricity to the national grid for roughly eight to 10 hours. Authorities said the temporary connection is designed to detect any technical faults before the first unit is fully integrated into the grid on November 21.
Officials confirmed that testing and verification of the reactor, turbines, and other critical systems have already been completed. During the initial stage, the plant is operating at just 3 percent of its capacity, using thermal energy from nuclear fuel to generate steam that drives the turbines.
Once capacity is gradually scaled up to 25–30 percent, the unit will be able to provide a steady supply of around 300 MW to the national grid.
Authorities noted that ongoing safety, technical, and performance checks will take another five to six months to bring the unit to full capacity after which commercial electricity generation will formally begin.